Special Finishes:
We installed a new three-story glass curtain wall, second- floor glass hand-rail, waterproof decking and parapet wall and flashing in the space. This project also featured new first-floor perimeter windows and re-waterproofing of existing façade with thin brick and flashing at each window, new perimeter base flashing throughout entire building, lath & plaster patching of existing exterior façade on four elevations, as well as coat with elastomeric coating and 166 new exterior windows at the second and third floors.

We installed two new 20-ton HVAC mechanical units on the roof, performed ADA upgrades to all interior restrooms and four new ADA restrooms , installed new interior corridor finishes, including carpet, paint, electrical remodel and new corridor and building standard door openings

The scope of this project also included remodelled parking garage lighting and a new security system.  

Difficult Tasks:
We were required to encroach onto main access points of Ygnacio Valley Road and North Broadway Street in Walnut Creek, manage traffic control, use scaffolding and swing gate of building. We also waterproofed an existing building that had a dilapidated façade, and leaking windows and flashings.  

Project Data
Client

Duration Area
Architect

Status
590 YVR Associates LLC 30 weeks 44,435 sq ft Studio Benavente Architects Complete